Water Project Progress - We Have Tanks!
The cement work on both pads is now complete. The first ten 2,500-liter water tanks have arrived at the Maya Jaguar campus and are ready to be installed. All of the required PVC piping and materials for the roofs has been ordered.
Installation is expected to be complete by March 20.



When complete, the project will consist of two concrete, roofed pads that will hold 12 and 18 tanks, adding a total of 75,000 liters (almost 20,000 gallons) of rainwater storage.
This is part of a Rotary International Global Grant and a volunteer effort by the